top of page

Our Work

This is our project's page, some of our more recent project's are uploaded to this page. This is to help customers see what is involved in the works. We also have links to the suppliers for the tanks so you can see how they operate and treat sewage.

01

Tricel Nova Treatment Plant Installation. 

Tank Offload.jpg

The team recently installed a Tricel NOVO 8 Pop near Marden. The existing sewage was going into an old septic tank that was not working and allowing ground water into the system. This was causing the tank and surrounding area to flood, not allowing the client to enjoy there garden as intended. 

​

We installed the tank, along with over 40 Meters of inlet pipework going around both sides of the house, aswell as 80 Meters of outlet pipe pumping the treated water into a ditch. 

​

Check out Tricel's website from the below link. 

Sewage Treatment Plants from Tricel. Strong & Durable

​

02

Graf Treatment Plant Installation 
 

In October 2023, we started work installing 2 Water Treatment plants and 2 rain water harverster tanks. 
Our first visit was to re-instate the outlet pipework from the house going back to the treatment plants that we installed. The plan will be to re-visit in early 2024 to install the 2 rain water harvester tanks. 
The 2 Graf water treatment plants are connected to a 100meter soakaway. 

03

​

WTE Quantum treatment plant installation

January 2025 we installed a Quantum treatment plant for one of our new customers who made contact with Kent Waste Water after seeing a social media post from a previous install we completed December 2024.. The install was completed within two and a half days, customer was extremely happy with the service received, we will return January 2026 to complete a yearly service. 

PHOTO-2025-02-03-16-53-26.jpg
PHOTO-2025-02-03-16-53-27.jpg
PHOTO-2025-02-03-16-53-19.jpg

04

​

100 pe Hipaff - Bude

November 2024 we installed a 100 pop hipaff treatment plant in Bude on behalf of another main contractor having been recommended by an associated company within the sewage industry. The install was completed within five days by a two man team discharging to a existing water course, there was six metres of inlet pipe directing the foul waste into the treatment plant and wired up by our in-house electrician.

Once wired in this system was commissioned by the company MD and the treatment plant was left fully operational. 

​

Due to the size of the treatment plant a crane was used to lower the system into the ground.

bude 2.jpg
bude 1.jpg
bude 3.jpg

05

​

BG Klargester - Rochester Golf Club

July 2024 we installed a BG Klargester treatment plant for Rochester and Cobham golf club after being recommended by a member but also one of Kent Waste Water customers who also had a install the previous year. 

​

The install was completed within four days with a four man team, the treatment plant discharges to the current soakaway which was working fine. A treatment plant was required due to the previous system coming to the end of its life and requiring a upgrade.

​

The system will be serviced on a six monthly basis to ensure everything is working correctly and remains under warranty.

​

Outcome of installing this treatment plant has resulted in Kent Waste water now installing a soakaway at the halfway point on the golf course.

 

 

 

​

rochester 4.jpg
rochester 3.jpg
rochester 1.jpg
rochester 2.jpg

06

​

RBC Refurb

A large RBC treatment plant that had failed after lack of maintenance carried out by another company. Kent waste water was found by the client via our social media posts and gave us the opportunity to quote and carry out the repair. Complete wash down of the system was completed with a new direct drive motor gearbox and tested leaving the system fully functioning. 

​

Regular servicing and maintenance alongside emptying has now been put in place.

​

​

refurb 2.jpg
refurb 3.jpg
refurb 1.jpg

07

​

Chichester 

Having being recommended to a national servicing provider Kent Waste water quoted to install a upgraded 30 pop treatment plant, replacing a failing treatment plant that come to the end of its life. Due to unstable ground and water our team had to install shoring so works could be carried out. All works were carried out within seven days start to finish and residents left with a non smelling system which was fully compliant.

chichester 1.jpg
chichester 2.jpg
chichester 4.jpg
chichester 3.jpg

©2023 Kent Waste Water Services

wpl.jpg
R.jpg
unnamedgraf.jpg
Tricel_Black Logo_Online use.png
OIP_edited.jpg
bottom of page